A textile manufacturing client in Tirupur required a 45,000 sq ft PEB facility with integrated administrative offices, a central corridor crane beam, and polycarbonate skylight ridges for natural lighting. The challenge: phased occupancy with production commencing in Phase 1 before Phase 2 construction started.
The Hexcentric Solution
Designed a structurally independent Phase 1 / Phase 2 PEB system with a shared expansion bay. Phase 1 (30,000 sq ft) was handed over in Week 7; Phase 2 (15,000 sq ft + offices) completed in Week 9 without interrupting production.